The basics
- Film-faced plywood gives smooth concrete; steel plates can be reused hundreds of times.
- Slabs sit on adjustable steel props spaced roughly 0.9–1.2 m apart.
- Usually priced per sq ft of slab area including labour, or rented by the day.
Shuttering and scaffolding types and price ranges in India
| Type | Specification | Best used for | Indicative price |
|---|---|---|---|
| Slab shuttering, labour and material | Plates, props, beams | Slabs and beams | ₹30–60 |
| Film-faced shuttering ply | 12–18 mm | Smooth slab and beam soffits | ₹45–80 |
| Steel shuttering plate (rental) | 600×900 mm | Repeated slab work | ₹3–6 |
| Adjustable steel prop (rental) | 2–3.5 m | Slab support | ₹2–5 |
| Scaffolding (cup-lock / pipe) | Rental | External plaster and paint | ₹3–6 |
| Shuttering oil / release agent | Mould release | Clean demoulding | ₹80–150 |
| Concrete mixer and needle vibrator | Rental | Site concreting | ₹800–2,500 |
Quality checks before you accept delivery
- Props must be vertical, on base plates or planks, with no bent tubes.
- Plates clean, oiled and tightly joined — gaps leak slurry and cause honeycombing.
- Check slab level from a fixed benchmark before steel is laid.
- Ply faces should be intact — torn film leaves a rough slab underside.
- Every prop needs its locking pin and a firm base.
- Measure slab depth and beam sizes at several points before the pour.
Pro tips
- IS 456 minimums with OPC: column sides 16–24 hours, slab props 7 days for spans up to 4.5 m and 14 days beyond, beam props 14–21 days.
- Keep one worker under the slab during the pour to watch for sagging props.
- Use a needle vibrator on every pour — hand tamping leaves voids.
- Tie scaffolding to the structure every few metres and add toe boards.
- Seal joints between plates with tape or foam so slurry can't leak.
- Keep a camber on long spans if your engineer specifies it.
Mistakes to avoid
- Removing props early to rush the next floor — the most common cause of sagging slabs.
- Pouring on dirty or unoiled plates, leaving rough, honeycombed concrete.
- Resting props directly on loose soil.
- Stacking bricks or cement bags on a slab less than a week old.
- Reusing warped ply on visible surfaces.
Where you can save
- Hiring a shuttering contractor per sq ft usually beats owning plates and props.
- Plan floor cycles so props move straight to the next slab instead of going back to the yard.